Power
Electrical Connection

The DEL AOP 50 has 4 available Knockouts for a 1/2” conduit fitting, two on the back and one on each side. Remove only the ideal Knockout for the installation and install the proper conduit fitting.
Connect the DEL AOP 50 to the pool timing clock so that the DEL AOP 50 operates simultaneously with the pool pump.
Grounding
Open the door by using a slotted screwdriver to turn the door latches a half-turn counterclockwise.
Locate the Terminal Block on the left side of the enclosure. Connect Line 1, Line 2, and Ground to the Terminal Block as indicated by the label on the Generator Bracket.
Create a Bond
Using a solid copper conductor, connect to the grounding lug on the left side of the DEL AOP 50 to an appropriate earth contact.
A pressure wire connector, labeled “bonding lugs”, is provided on the outside of the unit to permit connection to a minimum No. 6 AWG (13.3 mm2 ) solid bonding conductor between this point and any metal equipment, metal enclosures of electrical equipment, metal water pipes, or conduit within 5 feet (1.5 meters) of the unit.